History
The construction of the entire 71.16 km has been split into 6 stages with the first stage originally scheduled to be completed by March 2015
In November 2013, L&T Hyderabad Metro started laying of rails on the metro viaduct between Nagole and Mettuguda, a stretch of 8 km.
The first highly sophisticated train of the Hyderabad Metro Rail (HMR) came from Korea during the third week of May 2014. Stringent trial runs commenced from June 2014 till February 2015.The trial runs started on the Miyapur to Sanjeeva Reddy Nagar stretch in October 2015.
CMRS inspection for Stage-II (Miyapur and S.R.Nagar Section) was done on 9, 10 August 2016.Three interchanges are planned at Mahatma Gandhi Bus Terminus, Parade Grounds and Ameerpet.
The steel bridge of the HMR was successfully placed over the Oliphant bridge in August 2017.
In November 2017, Commissioner of Railway Safety (CMRS) granted safety approval for 12 km stretch from Miyapur to SR Nagar, 10 km stretch from SR Nagar to Mettuguda and 8 km stretch from Nagole to Mettuguda
In November 2013, L&T Hyderabad Metro started laying of rails on the metro viaduct between Nagole and Mettuguda, a stretch of 8 km.
The first highly sophisticated train of the Hyderabad Metro Rail (HMR) came from Korea during the third week of May 2014. Stringent trial runs commenced from June 2014 till February 2015.The trial runs started on the Miyapur to Sanjeeva Reddy Nagar stretch in October 2015.
CMRS inspection for Stage-II (Miyapur and S.R.Nagar Section) was done on 9, 10 August 2016.Three interchanges are planned at Mahatma Gandhi Bus Terminus, Parade Grounds and Ameerpet.
The steel bridge of the HMR was successfully placed over the Oliphant bridge in August 2017.
In November 2017, Commissioner of Railway Safety (CMRS) granted safety approval for 12 km stretch from Miyapur to SR Nagar, 10 km stretch from SR Nagar to Mettuguda and 8 km stretch from Nagole to Mettuguda